Gantt Chart Maker
Build your project schedule
Add task names, dates, one predecessor per task, and completion progress.
Turn a task list into a practical project schedule with dated bars, finish-to-start dependencies, and progress overlays. Add up to 24 tasks, set each start and end date, connect a task to one predecessor, and check the chart for invalid ranges, overlapping dependencies, or circular links. The timeline uses real calendar-day spacing, so a two-week gap is visibly longer than a two-day gap. When the schedule is ready, print it or export an SVG chart and a CSV task table.
How to make a Gantt chart
-
1
List the project tasks
Name the project, add task rows, and keep each task focused on one deliverable or activity.
-
2
Set dates and links
Enter each calendar date range and choose an optional predecessor to draw a finish-to-start dependency link.
-
3
Review and export
Update progress, resolve any date or dependency warnings, then download SVG or CSV or print the completed chart.
How the chart calculates task positions
A Gantt chart combines a task table with a horizontal time scale. This maker treats every accepted date as midnight UTC, which prevents daylight-saving changes from making one calendar day look shorter or longer than another. It finds the earliest task start and latest task end, then calculates each bar from three values:
start offset = (task start − project start) ÷ 86,400,000 milliseconds
bar width = inclusive task days ÷ inclusive project days × plot width
The end date is inclusive. A task that starts and ends on the same date therefore occupies one day rather than disappearing as a zero-width bar. The darker progress overlay uses bar width × progress ÷ 100, with progress constrained to 0 through 100.
Worked example
Suppose the project runs from January 1 through January 20, giving 20 inclusive calendar days and an 894-pixel plot. A Research task from January 1 through January 3 has an offset of 0 and a bar width of 3 ÷ 20 × 894 = 134.1 pixels. A Design task from January 5 through January 8 starts 4 ÷ 20 × 894 = 178.8 pixels into the plot; at 50% progress, its darker overlay is 89.4 pixels wide. A one-day Launch task on January 20 starts at 19 ÷ 20 × 894 = 849.3 pixels. If Design depends on Research, it must start on January 4 or later because the predecessor’s end date is included.
What the dependency check means
Each task can have one finish-to-start predecessor. In this common relationship, the successor should start after the predecessor’s inclusive end date. The editor draws a connector from the predecessor bar to the successor bar and reports a conflict when the successor starts on or before that date. It also detects self-links, missing predecessors, and dependency cycles such as A depending on B while B depends on A. These issues block export until they are corrected, but the chart remains visible to help diagnose the schedule.
| Check | Accepted | Reported as an issue |
|---|---|---|
| Date format | A real date from 1900 through 2200 | Missing or impossible date |
| Task range | End is on or after start | End is before start |
| Dependency | One existing predecessor that ends before the successor starts | Self-link, missing task, overlap, or cycle |
| Progress | 0 to 100 percent | Values are constrained to the supported range |
| Project size | Up to 24 task rows | Additional rows are refused |
Reading and sharing the result
Bar spacing is based on calendar days, not working days. Weekends and public holidays remain part of the scale. SVG preserves the vector chart for documents and presentations, CSV preserves the underlying task table, and Print lets the browser create paper output or a PDF. CSV cells that could be interpreted as spreadsheet formulas are prefixed as text before download.
This is a manual planning aid. It does not calculate a critical path, allocate resources, apply working calendars, support lead or lag, or automatically move successor dates. For those needs, use dedicated project scheduling software. Here, the dates you enter remain authoritative, and dependency warnings identify where manual correction is needed.
Frequently Asked Questions
Yes. A task from June 1 through June 3 is shown as three calendar days. A task with the same start and end date is shown as a one-day bar.
Each task can select one finish-to-start predecessor. The successor should start after the predecessor end date because both task ranges include their end dates. The tool reports overlaps instead of silently changing your dates.
Every task in the circular chain is marked with a dependency-cycle warning. Export and print controls remain unavailable until a predecessor is removed or changed.
No. The horizontal scale uses consecutive calendar days. The tool does not apply a working calendar, regional holidays, resource availability, lead, lag, or critical-path scheduling.
No. Project names, task names, dates, dependencies, and progress stay in browser memory and session storage. The tool does not place them in the page link or send them in requests to our servers. Closing the browser tab or session can remove the saved copy.
Related Tools
Mouse Tester
Test your mouse buttons, wheel scrolling, pointer movement and double-click timing in the browser. See event logs and movement samples without uploads.
Spacebar Counter
Count distinct spacebar presses or run a timed test with a target, timer, progress and presses-per-second estimate.
Fancy Serial Number Checker
Check US-style currency serial numbers for fancy patterns like radars, ladders, repeaters, low numbers and star notes.
Minecraft Circle Generator
Create hollow or filled Minecraft circle and ellipse blueprints. Set the block dimensions, count materials, inspect the grid and download an SVG.
Guitar Tuner
Tune a guitar in your browser with microphone pitch detection, cents offset, standard and alternate tunings, and no audio upload.
Metronome
Practice with a precise online metronome. Set BPM, meter, accent and subdivisions, then play a steady browser click locally.
Tool available in other languages
- Pembuat Bagan Gantt [ID]
- Trình tạo biểu đồ Gantt [VI]
- Criador de gráfico de Gantt [PT]
- منشئ مخطط جانت [AR]
- Kreator wykresów Gantta [PL]
- ガントチャートメーカー [JA]
- Gantt Grafiği Oluşturucu [TR]
- 간트 차트 만들기 [KO]
- เครื่องมือสร้างแผนภูมิแกนต์ [TH]
- Creador de diagramas de Gantt [ES]
- 甘特图制作工具 [ZH]
- Skapa Gantt-schema [SV]
- Créateur de diagramme de Gantt [FR]
- Gantt-diagram maken [NL]
- Gantt-Diagramm erstellen [DE]
- Creatore di diagrammi di Gantt [IT]
- Конструктор диаграмм Ганта [RU]